Deye GE-F120-2H2
A 122.8 kWh high-voltage LiFePO4 battery system delivering 50 kW of rated DC power for commercial backup and solar storage, expandable to 10 parallel units.
Technical Specifications
| Parameter | DEYE-GE-F120-2H2 |
|---|---|
| Battery Data | |
| Energy | 5.12 kWh |
| Module Energy | 5.12 kWh |
| System Energy | 122.8 kWh |
| Max. Capacity | 3600 kWh |
| Nominal Voltage | 51.2 V |
| Module Nominal Voltage | 51.2 V |
| Operating Voltage | 500-700 V |
| Rated Capacity | 100 Ah |
| Cell Chemistry | LiFePO4 |
| Cycle Life | >6000 |
| End-of-Life Capacity | 70% |
| Rated DC Power | 50 kW |
| Max. Charge Current | 36+36+36+36 A |
| Max. Discharge Current | 36+36+36+36 A |
| Max. Charge/Discharge Current | 36+36+36+36 A |
| Recommended Charge/Discharge Current | 100 A |
| Peak Discharge Current | 125 A |
| Max. Round-Trip Efficiency | 89% |
| Parallel Units | 10 |
| Protection Level | I |
| Warranty (Years) | 10 |
| Mechanical & Interface | |
| Communication Ports | CAN, RS485, Wi-Fi, ETH |
| Dimensions | 527 x 894 x 294 mm |
| Additional Notes | DC Injection current(mA): <0.5%ln; AC Output Frequency and V |
| Module Dimensions | 440 x 133 x 570 mm |
| Module Weight | 44 kg |
| Status Indicator | LCD |
| Weight | 2090 kg |
| Environment & Protection | |
| Charge Temperature | 0-55 °C |
| Discharge Temperature | -20 to 55 °C |
| Operating Humidity | 15-85 (non-condensing)% |
| Installation Location | Floor-Mounted |
| Enclosure IP Rating | IP55 |
| Storage Temperature | 0-35 °C |
| Working Temperature | -20 to 55 (>43 derating) °C |
Figures are measured at the test conditions the manufacturer’s datasheet states. A dash means the manufacturer publishes no figure for that model.
Availability & grid compliance in Spain
| Market | Spain |
| Grid authority / regulator | CNMC Spain |
| Quotation currency | EUR |
| Support hours timezone | Europe/Madrid |
| Delivery & installation coverage | Madrid, Barcelona, Valencia, Seville |
Figures on this page are the manufacturer's own, measured at the test conditions the datasheet states — they do not change by country. What changes is the approval that has to be met before the unit is energised: in Spain that is CNMC Spain. Confirm the grid code, import requirements and any local certification with them, or with us, before you order.
Key Features & Technical Highlights
- 122.8 kWh modular capacity: Assembled from 5.12 kWh LiFePO4 modules at 51.2 V each, the system reaches 122.8 kWh of storage.
- 50 kW rated DC power: Sustains 50 kW with a peak discharge current of 125 A for demanding commercial loads.
- High-voltage 500-700 V design: Pairs with high-voltage battery inverters across a 500-700 V DC operating window.
- IP55 floor-standing enclosure: Keeps dust and water jets away from the electronics in a floor-mounted cabinet.
- Over 6,000 charge cycles: Rated beyond 6,000 cycles to a 70% end-of-life threshold, under a stated 10-year warranty.
- Four communication channels: CAN, RS485, Wi-Fi and ETH ports connect the LCD-equipped system to monitoring.
Frequently Asked Questions
Which inverter class does the GE-F120-2H2 connect to?
It operates between 500 and 700 V DC, so it pairs with high-voltage battery inverters and power-conversion equipment - not with 48 V low-voltage hybrid inverters.
How large can a GE-F120-2H2 installation grow?
Up to 10 units can be connected in parallel, and the platform lists a maximum capacity of 3,600 kWh, so a site can start with one system and scale in stages.
What warranty and lifespan does the GE-F120-2H2 carry?
Deye states a 10-year warranty, a cycle life above 6,000 cycles and an end-of-life threshold of 70% of original capacity.
What temperatures can the GE-F120-2H2 work in?
It charges between 0 and 55 degrees C and discharges from -20 to 55 degrees C, with derating above 43 degrees; storage should stay between 0 and 35 degrees C at 15-85% non-condensing humidity.
How is the GE-F120-2H2 installed?
It is a floor-mounted system in an IP55 enclosure; each 5.12 kWh module weighs 44 kg and a complete system weighs 2,090 kg, so floor loading must be checked first.