Dubai's Push for Solar Energy: What Homeowners Should Know

MJS Team4 min read
Share:
Dubai skyline with solar panels on rooftops

What incentives are available for solar in Dubai? The UAE government is actively promoting solar energy adoption, and Dubai homeowners can benefit from several programs and incentives. Here's what you need to know in 2026.

Shams Dubai: The Net Metering Program

Shams Dubai is DEWA's initiative that allows homeowners to install solar panels and connect them to the grid. Under this program:

  • Excess electricity is exported to the DEWA grid
  • You receive credits on your electricity bill
  • No batteries required (though recommended for backup)
  • DEWA handles the connection and metering

How Net Metering Works

When your solar panels produce more electricity than you use, the excess flows to the grid. Your meter runs backward, giving you credits. At the end of the billing period, you only pay for the net electricity consumed.

Financial Benefits for Homeowners

Dubai homeowners installing solar can expect:

  • 30-50% reduction in electricity bills
  • 7-10 year payback period depending on system size
  • 25+ year system lifespan for quality panels
  • Increased property value with solar installation

UAE Clean Energy Strategy 2050

The UAE aims to produce 50% of its energy from clean sources by 2050. This long-term commitment means continued support for residential solar adoption. Recent developments include:

  • Expanded DEWA customer service for solar applications
  • Streamlined approval process (now 2-4 weeks)
  • Growing network of certified installers
  • New financing options for solar installations

Getting Started with Solar in Dubai

The process for installing solar in Dubai involves:

  1. Assessment: Evaluate your roof space and energy needs
  2. Design: Work with a certified installer for system design
  3. Approval: Submit application to DEWA (2-4 weeks)
  4. Installation: Professional installation (1-3 days)
  5. Connection: DEWA inspection and grid connection

Why 2026 is a Good Year for Solar

Several factors make 2026 an excellent time to go solar in Dubai:

  • Solar panel prices have dropped significantly
  • Battery technology has improved and costs are down
  • Electricity rates continue to rise
  • Government support remains strong

How MJS Can Help

At MJS, we simplify the solar journey. Our team helps you find the right solar battery solution, connects you with certified installers, and guides you through the DEWA application process. Contact us for a free consultation.

Frequently Asked Questions

What is Shams Dubai?

Shams Dubai is DEWA's net metering program that allows Dubai homeowners to install solar panels and connect them to the grid. Excess electricity is exported to DEWA, and homeowners receive credits on their electricity bills.

How much can I save with solar in Dubai?

Dubai homeowners can save 30-50% on electricity bills with solar panels. The typical payback period is 7-10 years, after which electricity is essentially free for the 25+ year lifespan of the system.

How long does it take to install solar in Dubai?

The complete solar installation process in Dubai takes 4-8 weeks: 2-4 weeks for DEWA approval, 1-3 days for installation, and a few days for inspection and grid connection.